Unit commitment constraints in long-term planning models: Relevance, pitfalls and the role of assumptions on flexibility

Journal Contribution - Journal Article

- Not considering alternative sources of flexibility can lead to significant errors. - Unit commitment constraints have limited impact with alternative flexibility sources. - Unit commitment constraints mainly impact investments in storage technologies. - Sensitivity to assumed flexibility of power plants and reserve requirements is high. - Errors due to approximate formulations are small compared to the sensitivities.
Journal: Applied Energy
ISSN: 0306-2619
Volume: 258
Publication year:2020
BOF-keylabel:yes
IOF-keylabel:yes
BOF-publication weight:10
CSS-citation score:3
Authors from:Higher Education
Accessibility:Open