A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations

Journal Contribution - Journal Article

The purpose of this research is to develop a new procedure for generating a proactive baseline schedule for the resource-constrained project scheduling problem. The main advantage of this new procedure is that it is completely independent of the reactive policy applied. This contrasts with the traditional methods that assume a predefined reactive policy. First, we define a new robustness measure, then we introduce a branch-and-cut method for solving a sample average approximation of our original problem. In a computational experiment, we show that our procedure outperforms two other published methods, assuming different robustness measures.
Journal: Journal of Scheduling
ISSN: 1094-6136
Issue: 4
Volume: 19
Pages: 409 - 428
Publication year:2016
BOF-keylabel:yes
IOF-keylabel:yes
BOF-publication weight:1
CSS-citation score:3
Authors from:Higher Education
Accessibility:Open